150 TPD Cottonseed Oil Refining Project in Uzbekistan

150 TPD Cottonseed Oil Refining Project in Uzbekistan

A 150 TPD chemical refining line added to an existing cottonseed crushing facility in Uzbekistan, including caustic refining, bleaching, deodorization and soap stock splitting.

Uzbekistan is one of the world's largest cotton producers, and the client already operates a 150 TPD cottonseed crushing facility. The addition of a refining train allows them to capture the value of the crude oil internally rather than selling it to refiners at a discount.

The refining line is conventional chemical refining: phosphoric acid degumming → caustic neutralization → bleaching earth → deodorization (250°C, 3 mbar) → cooling → polish filtration. Soap stock is split into fatty acid using a high-pressure splitter; the fatty acid is sold to the local soap industry.

Local climate matters in Tashkent — extreme heat in summer, cold winters. The line includes pre-insulation, redundant cooling water pumps, and a winterization package that allows continuous operation down to -15°C ambient.

The line has been running since 2022. The client's gross margin on refined oil is approximately 22% higher than on crude oil sales, with annual incremental EBITDA of around USD 2.5 million at 90% utilization.

Project Specifications

Key data about this installation. The data sheet is included with the technical proposal we send during inquiry.

Project data sheet for 100 T/D Palm Oil Refining and Fractionation in Congo
Parameter Value
Capacity100 T/D (refined oil)
Raw materialCrude palm oil (CPO)
Final productsRBD palm olein, RBD palm stearin, PFAD
LocationCongo (Brazzaville)
Project typeRefining & fractionation
Commissioning year2022

Interested in a Similar Project?

Contact our engineering team to discuss your production requirements. We deliver customized EPC solutions worldwide.

Send Us a Message

Fill in your project details below — our engineering team typically responds within 48 hours with a customized proposal and preliminary process flow diagram.

We respect your privacy. Your information is used only to prepare your project proposal and will never be shared with third parties.

Response within 48 hours
Your data is secure & confidential
Free, no-obligation proposal